October 2004
Project application approved
Dec 04 - March 05
Meetings with partners
March 05
Transnational partnership formed
April 05
Full Development Partnership Formed
June 05
Action 2 Approval received
Action 1 ends
July 05
Action 2 Starts
October 05
First prototype module lesson produced
November 05
Transnational partnership approved
Full DP meeting
Nov 05 – Jan 06
Developing first module
February 06
Disability module released
Full DP meeting
April 06
Gender module released
July 06
Age module released
October 06
Welsh Language module released
Moderators Programme developed
January 07
Religion and Belief module released
March 07
Sexual Orientation module released
July 07
September 07
Dissemination starts
October 07
Final Transnational Partner meeting in Portugal
November 07
Conference in Cardiff
December 07
Conference in Llandudno
Actions 2 and 3 end